• Share :

Engineering Services for Civil, Structural and Building Works of Jawa 2 Combined Cycle Power Plant Project for Mitsubshi Hitachi Power System

Mitsubishi Hitachi Power Systems, Ltd. (here inafter called MHPS) has already been awarded by PLN as the winner of the bidding process for Jawa-2 800 MW Combined Cycle Power Plant (CCPP) Project. The Project Site is located in Tanjung Priok in the north-east portion of Jakarta City, approximately 10 km from central part of Jakarta City and 20 km east of Soekarno-Hatta International Airport.

MHPS has appointed PT Bita Enarcon Engineering (BITA) for providing Engineering Services for Civil, Structural and Building Works of Jawa-2 Combined Cycle Power Plant Project.  The scope of works shall cover but not lmited to:
-    Structural calculations
-    Detailed Engineering Design (DED) drawings documentation consist of :

  • Architectural drawings
  • Concrete structural drawings
  • Steel structural, platform & staircase drawings
  • Drainage drawings
  • Site Grading & Underground Utilities drawings